General Information

K-RERA/PRJ/ERN/055/2024
CH Vaikund
Akshay S Kamath
Residential (Apartment)
07/07/2025
Click Here

Quarterly updated values

Project Information

CH Vaikund
Residential (Apartment)
01/02/2024
30/04/2026
Yes
No

Land Details

799.70
1
2378.54
2378.54
0
20
0

Location Details of the Project Area

214/3-88
19716
KERALA
Ernakulam
Kanayannur
POONITHURA
South Janatha Road
Karnakodam
682032
Corporation Road - South Janatha Road
MD Jacob
KJ Kamath Lane
Private Access of Rajesh R Pai

Mortgages

Promoter's Information - Individual

Akshay
S
Kamath
R SREEKUMAR KAMATH
Yes

Permanent address of the Promoter

Chandrus Housing Projects, 64/3492
Azad Road
Kaloor
Chandrus Building
KERALA
Ernakulam
Kanayannur
682017

Address For Official Communication

Chandrus Housing Projects, 64/3492
Azad Road
Kaloor
Chandrus Building
KERALA
Ernakulam
Kanayannur
682017

Contact Details

9744722444
chprojects.ekm[at]gmail.com
Member Name Designation Address Contact Email Photo
Akshay S Kamath Authorized Signatory Gowraghar, Gopala Prabhu Road, , Kanayannur, KERALA, 682035 9744722444 chprojects.ekm@gmail.con View Photo
Akshay S Kamath Proprietor Gowraghar, GP Road, , Kanayannur, KERALA, 682035 9048363802 akshaykamath9523@gmail.com View Photo

Land owner details

Land owner Name Type of Land Owner PAN Number Type of Agreement/ Arrangement CreatedOn Office Number (With area code) Other Details

Promoter's Past Experience Details

Sr No. Project Name RERA registration number Project Address Land Area (In Sq mtrs) Details of payments pending Current status of the project Details of cases/ litigations related to the project Date of commencement Proposed date of completion Actual completion date Remarks (If any) Other relevant experience
1 Ravindram K-RERA/PRJ/237/2020 Deshabhimani Road 607 0 Completed 0 27/10/2020 26/10/2022 26/03/2022 NA NA

Building Permit Details

Building Permit Number Dated Type Date of Expiry Issued by Name of the Local body/ LSGI

Development Permit Details

Building Details

Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 CH Vaikund 30/04/2026 0 0 5 30 1 13

Apartments/Villas Type Details

Sr.No. Apartment/Villa Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 2BHK 61.40 0 2.60 0 19.82 2.60 85.94 4
2 3BHK 82.77 0 9 0 27.40 2.55 121.72 4
3 3BHK 83.10 0 5.68 0 28.50 3.50 120.78 4
4 2BHK 54.62 0 8.62 0 18 2.38 83.62 4
5 2BHK 60.71 0 5 0 20 2.09 87.80 4

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Stilt Floor
4 Slabs of Super Structure
5 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
6 Sanitary Fittings
7 Electrical Fittings
8 Staircases, Lifts Wells
9 Overhead and Underground Water Tanks.
10 The external plumbing and external plastering
11 Completion of terraces floor each building
12

Installation of lifts, water pumps etc

13

Fire Fighting Fittings and Equipment

14

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Common Areas and Facilities

Project Details

Name Proposed Number Progress of work done (In %)
Current value Last Quarter value
Number of Garages/ Covered Parking (In Numbers) (Common Area) :

Development Work

Common areas And Facilities, Amenities Proposed Percentage of completion Details
Current value Last Quarter value
Association room :
Open parking :
Sign Boards :
Water supply :
Reticulated Gas Supply :
Water conservation, Rain water harvesting :
Fire protection and Fire safety requirements :
Security cameras :
Sewerage (Chamber, Lines, Septic tank, STP) :
Visitors Parking :
Aggregate area of recreational open space :
Electrical meter room, Sub-station, Receiving station :
Energy Management :
Lift :
Solar systems :

Professional Information

Professional Name RERA Certificate No. Professional Type Type of Contractor Registration Number Name of the firm Address of the firm Year of establishment Name of Promoters Associated with Key projects completed Type of Professional
Ninitha Elsa Saji NA Architect NA CA/2021/130554 NES Designs Ponuruni 2019 - Ravindram NA
Hari G NA Engineer NA NA CGL Geoinformatics CGL Complex, Ernakulam-19 1992 - Ravindram NA
Sreenathh T Lal NA Chartered Accountant NA FRN-014992S RMSt & Co Sreenilayam, Kottecanal Road, Ernakulam-18 2017 - Ravindram NA

Uploaded Documents

Document Name Uploaded Document Remarks Uploaded Date
PROJECT DETAILS
Copy of Sanctioned Plans 15/01/2024 19:43:00
Copy of Valid Building Permit 15/01/2024 19:42:35
Copy of Valid Development Permit (For villa projects & plot development pojects) Not Applicable 15/01/2024 19:48:15
Detailed technical specifications to be adopted in the project 23/02/2024 12:18:49
Detailed technical specifications to be adopted in the project 23/02/2024 12:25:30
Layout approval plan
Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points 23/02/2024 13:58:11
Site Plan / Site Map
LAND DETAILS
Copy of latest Land Tax Receipt 15/01/2024 19:43:59
Copy of Title Deed 15/01/2024 19:43:43
Land title search report (From an advocate as specified in Rule 17) NA 05/02/2024 14:09:19
Land title search report (From an advocate as specified in Rule 17) 23/02/2024 10:32:28
Latest Encumbrance certificate 15/01/2024 19:44:16
Proforma of Conveyance Deed / Sales Deed 05/02/2024 20:28:07
PROMOTER DETAILS
Declaration / Affidavit in Form B 05/02/2024 20:37:40
Declaration / Affidavit in Form B 23/02/2024 10:34:01
The annual report including audited profit and loss account, balance sheet, cash flow statement, directors report and auditor's report of the promoter for the immediately preceding three financial years and where annual report is not available then the audited profit and loss account, balance sheet, cash flow statement and the auditor's report of the promoter for immediately preceding three financial years and in case of newly incorporated or registered entity, such information shall be disclosed for the parent entity.
ALLOTMENT DETAILS
Proforma of Agreement for Sale (As per Annexure A) Note - Promoter is directed to stick on original clauses of Annexure A. No alterations/additions/omissions are allowed in words/sentences/clauses. 05/02/2024 20:27:33
Proforma of Agreement for Sale (As per Annexure A) Note - Promoter is directed to stick on original clauses of Annexure A. No alterations/additions/omissions are allowed in words/sentences/clauses. 23/02/2024 10:45:35
Proforma of Allotment Letter (As per the Authority order No. K-RERA/T1/1657/2024 dated 26/11/2024) NA 05/02/2024 20:27:45
ARCHITECT,ENGINEER & CA Certificates
Architect's Certificate in Form No 2 12/07/2024 19:30:50
Architect's Certificate in Form No 2 07/10/2024 22:33:15
Architect's Certificate in Form No 2 07/01/2025 12:36:03
Architect's Certificate in Form No 2 07/04/2025 19:59:22
Architect's Certificate in Form No 2 07/07/2025 21:28:08
Chartered Accountant's Certificate in Form No 4 (in letter head) 12/07/2024 19:32:39
Chartered Accountant's Certificate in Form No 4 (in letter head) 07/10/2024 22:33:59
Chartered Accountant's Certificate in Form No 4 (in letter head) 07/01/2025 12:36:47
Chartered Accountant's Certificate in Form No 4 (in letter head) 07/04/2025 20:00:07
Chartered Accountant's Certificate in Form No 4 (in letter head) 07/07/2025 21:28:56
Engineer's Certificate in Form No 3 12/07/2024 19:32:57
Engineer's Certificate in Form No 3 07/10/2024 22:34:37
Engineer's Certificate in Form No 3 07/01/2025 12:37:11
Engineer's Certificate in Form No 3 07/04/2025 20:01:07
Engineer's Certificate in Form No 3 07/07/2025 21:29:53
NOC and other Clearance
Clearance from Airport Authority of India Not Applicable 15/01/2024 19:50:12
Clearance from Airport Authority of India Not Applicable, since the project does not require the NOC depending on the distance and also the building height 23/02/2024 10:54:37
Clearance from Coastal Zone Management Authority Not Applicable 15/01/2024 19:50:48
Clearance from Coastal Zone Management Authority Not Applicable, since the project the outside the limits of the lines set by CRZ and does not come under the rules set by it 23/02/2024 10:55:59
Clearance from National Highways / Railways / Other Relevant Departments Not Applicable 15/01/2024 19:50:28
Clearance from National Highways / Railways / Other Relevant Departments Not Applicable, since the project is not near any of theses department zones. 23/02/2024 10:56:59
Concurrence / Layout Approval of LSG planning department Not Applicable 15/01/2024 19:49:03
Concurrence / Layout Approval of LSG planning department Not Applicable, since the project does not fall under these approvals 23/02/2024 10:57:58
Consent to establish (Clearance from Pollution Control Board) 15/01/2024 19:45:00
Environment Clearance Not Applicable 15/01/2024 19:48:45
Environment Clearance Not Applicable, since the Environment clearance rules is not applicable for this project 23/02/2024 10:59:05
If the project is proposed to be developed in Phases, an authenticated copy of license or land use permission, Building sanction plan or building permit for each of such phases (If applicable)
Initial NOC from Fire and Rescue department 15/01/2024 19:46:29
Permission from Water and sewerage department Not Applicable 15/01/2024 19:49:52
Permission from Water and sewerage department Not Applicable, since these permissions are not required for the project 23/02/2024 10:59:59
BROCHURE & OTHER DETAILS
Others Form 1 Updated 23/02/2024 10:52:29
Others 23/02/2024 12:26:51
Sanction letters from Bank for construction finance
Sanction letters from bank for home loan tie-ups
PLAN OF DEVELOPMENT WORKS
Charts and the project schedule 23/02/2024 12:17:41
List and details of common amenities 23/02/2024 12:17:29
Other Plans to be executed in the proposed project
Plan for Drinking water service to be executed in the proposed project
Plan of firefighting to be executed in the proposed project 23/02/2024 11:01:35
Plan of Use of renewable energy to be executed in the proposed project 23/02/2024 11:02:07
BROCHURE & OTHER DETAILS
Brochure / prospectus issued in regard to this project
Completion plan (if any)
Consent to operate (Clearance from Pollution Control Board)
Declaration by the Promoter - Form No. 6
Details of the Association formed
Development certificate(for plots and villas)
Final Fire NOC
Occupancy Certificate
Land Owner Details
Registered Joint Development Agreement 26/01/2024 10:58:33
Registered Joint Development Agreement 23/02/2024 10:49:20

Upload Photograph

Document Name Uploaded Document Uploaded Date
Photograph of each building 07/07/2025 21:34:30
Photograph of each building 07/07/2025 21:34:15
Photograph of each building 07/04/2025 20:15:13
Photograph of each building 07/04/2025 20:15:03
Photograph of each building 07/04/2025 20:14:55
Photograph of each building 07/04/2025 20:14:46
Photograph of each building 07/04/2025 20:14:34
Photograph of each building 07/04/2025 20:14:21
Photographs of common areas and internal infrastructure 07/01/2025 12:45:04
Photographs of common areas and internal infrastructure 07/01/2025 12:44:37
Photographs of common areas and internal infrastructure 07/01/2025 12:44:27
Photographs of common areas and internal infrastructure 07/01/2025 12:44:15
Photographs of common areas and internal infrastructure 07/10/2024 22:30:46
Photographs of common areas and internal infrastructure 07/10/2024 22:30:36
Photographs of common areas and internal infrastructure 07/10/2024 22:30:22
Photographs of common areas and internal infrastructure 12/07/2024 19:28:47
Photographs of common areas and internal infrastructure 12/07/2024 19:28:47
Photographs of common areas and internal infrastructure 12/07/2024 19:28:29

Litigations Related to the Project