General Information

K-RERA/PRJ/321/2020
ASTEN CAMPUS COURT
ASTEN REALTORS PRIVATE LIMITED
Residential (Apartment)
07/01/2025
Click Here

Quarterly updated values

Project Information

ASTEN CAMPUS COURT
Residential (Apartment)
01/02/2012
10/03/2023
Yes
No

Land Details

14123
2
75131.03
75131.03
0
368
0

Location Details of the Project Area

Re-Survey No. 563/12-3,12-4,12-1, Block No. 9
4170,5442
KERALA
Ernakulam
Kanayannur
KAKKANAD
RAJAGIRI VALLEY ROAD
CHITTETHUKARA
682039
PROPERTY OF SOUTH INDIAN BANK LTD.
CANAL
PROPERTY OF ASTEN MALLS LTD.
MUNICIPALITY ROAD

Mortgages

Promoter's Information - Other Than Individual


Company
ASTEN REALTORS PRIVATE LIMITED
Yes
No

Registered address of the Promoter

28 ASTEN, 2ND FLOOR
NH BYE PASS
PALARIVATTOM
OPP. SPICES BOARD
KERALA
Ernakulam
Kanayannur
COCHIN CORPORATION
682028

Address for official communication

28 ASTEN, 2ND FLOOR
NH BYE PASS
PALARIVATTOM
OPP. SPICES BOARD
KERALA
Ernakulam
Kanayannur
COCHIN CORPORATION
682028
Member Name Designation Photo
SIRAJ MATHER Managing Director View Photo
SIRAJ MATHER Authorized Signatory View Photo
RAFFI MATHER Director View Photo

Land owner details

Land owner Name Type of Land Owner PAN Number Type of Agreement/ Arrangement CreatedOn Office Number (With area code) Other Details

Promoter's Past Experience Details

Sr No. Project Name RERA registration number Project Address Land Area (In Sq mtrs) Details of payments pending Current status of the project Details of cases/ litigations related to the project Date of commencement Proposed date of completion Actual completion date Remarks (If any) Other relevant experience
1 ASTEN VIVERIA KAKKANAD 1114 NONE COMPLETED NONE 04/02/2015 19/02/2020 19/02/2020 NA NA

Building Permit Details

Building Permit Number Dated Type Date of Expiry Issued by Name of the Local body/ LSGI

Development Permit Details

Building Details

Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 CAMPUS COURT TOWER 1 10/09/2022 0 3 26 1 0 184

Apartments/Villas Type Details

Sr.No. Apartment/Villa Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 3BHK 105 0 7.83 0 38.62 0 163.57 132
2 2BHK 90.78 0 6.75 0 37.47 0 146.09 2
3 3BHK 104.62 0 4.87 13.81 38.62 0 163.57 6
4 3BHK 92 0 6 0 37.47 0 146.09 44

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 184 2782 155 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Installation of lifts, water pumps etc

12

Fire Fighting Fittings and Equipment

13

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 CAMPUS COURT TOWER 2 10/09/2022 0 3 26 1 0 184

Apartments/Villas Type Details

Sr.No. Apartment/Villa Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 3BHK 104.62 0 4.87 13.81 38.62 0 163.57 6
2 3BHK 105 0 7.83 0 38.62 0 163.57 132
3 2BHK 90.78 0 6.75 0 37.47 0 146.09 2
4 2BHK 92 0 6 0 37.47 0 146.09 44

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 184 2782 159 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Installation of lifts, water pumps etc

12

Fire Fighting Fittings and Equipment

13

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Common Areas and Facilities

Project Details

Name Proposed Number Progress of work done (In %)
Current value Last Quarter value
Number of Garages/ Covered Parking (In Numbers) (Common Area) 368

Development Work

Common areas And Facilities, Amenities Proposed Percentage of completion Details
Current value Last Quarter value
ROOF TOP PARTY AREA :
Water conservation, Rain water harvesting :
Landscaping & Tree planting :
Open parking :
Water supply :
Aggregate area of recreational open space :
Electrical meter room, Sub-station, Receiving station :
Internal Roads & Footpaths :
SWIMMING POOL :
Fire protection and Fire safety requirements :
GYM :
OUTDOOR PLAY AREA :
Sewerage (Chamber, Lines, Septic tank, STP) :
Storm water drains :
Street lighting :
Visitors Parking :

Professional Information

Professional Name RERA Certificate No. Professional Type Type of Contractor Registration Number Name of the firm Address of the firm Year of establishment Name of Promoters Associated with Key projects completed Type of Professional
TILAK THOMAS NA Architect NA CA99/25282/2000 THOMAS ASSOCIATES 32, KASTURBA CROSS ROAD, SHANTHALA NAGAR, ASHOK NAGAR, BANGALORE-56001 1999 FORUM FORUM MALL NA
K M NAZEER NA Engineer NA M1574137 NA NA 2010 NA TALUK HOSPITAL KODUNGALLOOR NA

Uploaded Documents

Document Name Uploaded Document Remarks Uploaded Date
Land Owner Details
Registered Joint Development Agreement 24/03/2021 15:10:40

Upload Photograph

Document Name Uploaded Document Uploaded Date
Photograph of each building 07/01/2025 18:35:09
Photograph of each building 07/01/2025 18:33:55
Photograph of each building 07/01/2025 18:33:09
Photograph of each building 07/01/2025 18:32:51
Photograph of each building 07/01/2025 18:32:08
Photograph of each building 07/01/2025 18:31:43
Photograph of each building 07/01/2025 18:31:11
Photograph of each building 07/01/2025 18:30:53
Photograph of each building 07/01/2025 18:30:34
Photograph of each building 07/01/2025 18:30:15
Photograph of each building 07/01/2025 18:29:57
Photograph of each building 07/01/2025 18:29:38
Photograph of each building 07/01/2025 18:29:22
Photographs of common areas and internal infrastructure 07/10/2024 18:02:15
Photographs of common areas and internal infrastructure 07/10/2024 18:02:01
Photographs of common areas and internal infrastructure 07/10/2024 18:01:45
Photograph of each building 07/10/2024 18:01:26
Photograph of each building 07/10/2024 18:01:10
Photograph of each building 07/10/2024 18:00:10
Photograph of each building 07/10/2024 17:59:47

Litigations Related to the Project

Name Of The Court Petition Type Case Number Year Present Status Orders
K-RERA Adjudicating Joe Philips and another 118/2020 2020 Final Judgement
K-RERA Authority Joe Philip 64/2022 2022 Final Judgement