General Information

K-RERA/PRJ/ERN/077/2023
OMG SOVEREIGN VILLAS
OMG PROPERTIES PRIVATE LIMITED
Villas (Plots & Buildings)
29/05/2025
Click Here

Quarterly updated values

Project Information

OMG SOVEREIGN VILLAS
Villas (Plots & Buildings)
15/10/2022
31/10/2027
Yes
No

Land Details

2739
16
1600
1600
0
16
0

Location Details of the Project Area

320/12-2,320/13-2
7924,9594
KERALA
Ernakulam
Aluva
KARUKUTTY
Karyamparambu
near karayamparambu signal, beside federal city apartments
683576
property of pynadath peter , saji pv
property of poothamkutty parambil , chittinappilly poulose, and vazhy to panchayat road
property of vakkayil sreedharan nair
property of chittinapally martha

Mortgages

Promoter's Information - Other Than Individual


Company
OMG PROPERTIES PRIVATE LIMITED
Yes
No

Registered address of the Promoter

18/465-19,FIRST FLOOR
VICTORY CORNER
KOPPAM
KOPPAM VILLAGE OFFICE
KERALA
Palakkad
Palakkad
PALAKKAD MUNCIPALITY
678001

Address for official communication

18/465-19,FIRST FLOOR
VICTORY CORNER
KOPPAM
KOPPAM VILLAGE OFFICE
KERALA
Palakkad
Palakkad
PALAKKAD MUNCIPALITY
678001
Member Name Designation Address Contact Email Photo
SURESH V Authorized Signatory VANOPADATH,PULAPPATTASHERI, CHERUMUNDASSERY, , Ottappalam, KERALA, 679512 9072345255 sureshomgproperties@gmail.com View Photo
RAJANEESH V G NAIR Managing Director NELLIKKAPARAMBIL HOUSE, KK ROAD, , CHALAKKUDY, KERALA, 680307 9843620400 rajani.ve@gmail.com View Photo
GIREESH S Managing Director NO.A 102, VEDAM ENCLAVE, PATTANAM LTTERY ROAD, , Coimbatore South, TAMIL NADU, 641016 9843293237 gireesh7@gmail.com View Photo

Land owner details

Land owner Name Type of Land Owner PAN Number Type of Agreement/ Arrangement CreatedOn Office Number (With area code) Other Details

Promoter's Past Experience Details

Sr No. Project Name RERA registration number Project Address Land Area (In Sq mtrs) Details of payments pending Current status of the project Details of cases/ litigations related to the project Date of commencement Proposed date of completion Actual completion date Remarks (If any) Other relevant experience
1 NIL NIL 0 0 0 O 12/09/2018 18/03/2022 NA 0 0

Building Permit Details

Building Permit Number Dated Type Date of Expiry Issued by Name of the Local body/ LSGI

Development Permit Details

Development Permit Number Dated Type Date of Expiry Issued by Name of the Local body/ LSGI

Building Details

Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 SG01 01/10/2027 1 1 2 0 1 0

Apartments/Villas Type Details

Sr.No. Apartment/Villa Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 80 5 5 0 0 10 100 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Installation of lifts, water pumps etc

12

Fire Fighting Fittings and Equipment

13

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 SG02 01/10/2027 1 1 2 0 1 0

Apartments/Villas Type Details

Sr.No. Apartment/Villa Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 80 5 5 0 0 10 100 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 SGO3 01/10/2027 1 1 2 1 1 0

Apartments/Villas Type Details

Sr.No. Apartment/Villa Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 80 5 5 0 0 10 100 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 SG04 01/10/2027 1 1 2 0 1 0

Apartments/Villas Type Details

Sr.No. Apartment/Villa Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 80 5 5 0 0 10 100 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
5 SG05 01/10/2027 1 1 2 0 1 0

Apartments/Villas Type Details

Sr.No. Apartment/Villa Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 80 5 5 0 0 10 100 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
6 SG06 01/10/2027 1 1 2 0 1 0

Apartments/Villas Type Details

Sr.No. Apartment/Villa Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 80 5 5 0 0 10 100 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
7 SG07 01/10/2027 1 1 2 0 1 0

Apartments/Villas Type Details

Sr.No. Apartment/Villa Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 80 5 5 0 0 10 100 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
8 SG08 01/10/2027 1 1 2 0 1 0

Apartments/Villas Type Details

Sr.No. Apartment/Villa Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 80 5 5 0 0 10 100 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
9 SG09 01/10/2027 1 1 2 0 1 0

Apartments/Villas Type Details

Sr.No. Apartment/Villa Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 80 5 5 0 0 10 100 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
10 SG10 01/10/2027 1 1 2 0 1 0

Apartments/Villas Type Details

Sr.No. Apartment/Villa Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 80 5 5 0 0 10 100 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
11 SG11 01/10/2027 1 1 2 0 1 0

Apartments/Villas Type Details

Sr.No. Apartment/Villa Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 80 5 5 0 0 10 100 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Installation of lifts, water pumps etc

12

Fire Fighting Fittings and Equipment

13

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
12 SG12 01/10/2027 1 1 2 0 1 0

Apartments/Villas Type Details

Sr.No. Apartment/Villa Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 80 5 5 0 0 10 100 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
13 SG14 01/10/2027 1 1 2 0 1 0

Apartments/Villas Type Details

Sr.No. Apartment/Villa Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 80 5 5 0 0 10 100 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
14 SG15 01/10/2027 1 1 2 0 1 0

Apartments/Villas Type Details

Sr.No. Apartment/Villa Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 80 5 5 0 0 10 100 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
15 SG16 01/10/2027 1 1 2 0 1 0

Apartments/Villas Type Details

Sr.No. Apartment/Villa Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 80 5 5 0 0 10 100 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
16 SG17 01/10/2027 1 1 2 0 1 0

Apartments/Villas Type Details

Sr.No. Apartment/Villa Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 80 5 5 0 0 10 100 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Installation of lifts, water pumps etc

12

Fire Fighting Fittings and Equipment

13

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Plot Details

Area of Plot (In sqmts) Number of Plots Number of Plots Booked / Alloted / Sold
Current value Last Quarter value
2739 16 13 NA

Common Areas and Facilities

Project Details

Name Proposed Number Progress of work done (In %)
Current value Last Quarter value
Number of Garages/ Covered Parking (In Numbers) (Common Area) 0

Development Work

Common areas And Facilities, Amenities Proposed Percentage of completion Details
Current value Last Quarter value
Security cameras :
Street lighting :
Landscaping & Tree planting :
Sign Boards :
Water supply :
Internal Roads & Footpaths :

Professional Information

Professional Name RERA Certificate No. Professional Type Type of Contractor Registration Number Name of the firm Address of the firm Year of establishment Name of Promoters Associated with Key projects completed Type of Professional
Hammad Hussain NA Architect NA CA/2020/122663 DE FLOW architects kozhikode 2020 omg properties na NA
ANU Soman NA Engineer NA E4947/15/EA/1047/KLM NA na 2010 omg properties omg lifestyles NA
Radhakrishnan P NA Chartered Accountant NA 217128 na same 2010 same same NA

Uploaded Documents

Document Name Uploaded Document Remarks Uploaded Date
PROJECT DETAILS
Copy of Sanctioned Plans 09/11/2022 13:08:27
Copy of Sanctioned Plans 16/02/2023 17:50:04
Copy of Sanctioned Plans 16/02/2023 17:52:20
Copy of Sanctioned Plans 16/02/2023 17:57:02
Copy of Valid Building Permit 09/11/2022 13:09:06
Copy of Valid Building Permit 16/02/2023 14:52:51
Copy of Valid Development Permit (For villa projects & plot development pojects) 09/11/2022 13:09:20
Detailed technical specifications to be adopted in the project 27/03/2023 16:26:39
Layout approval plan 09/11/2022 13:09:50
Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points 04/03/2023 15:44:02
Site Plan / Site Map
LAND DETAILS
Copy of latest Land Tax Receipt 09/11/2022 13:10:16
Copy of latest Land Tax Receipt 24/04/2023 16:22:54
Copy of Title Deed 09/11/2022 13:11:36
Copy of Title Deed 09/11/2022 13:13:06
Land title search report (From an advocate as specified in Rule 17) 22/02/2023 16:31:27
Latest Encumbrance certificate 22/02/2023 16:32:43
Proforma of Conveyance Deed / Sales Deed 22/02/2023 16:23:09
PROMOTER DETAILS
Declaration / Affidavit in Form B 15/11/2022 10:04:54
The annual report including audited profit and loss account, balance sheet, cash flow statement, directors report and auditor's report of the promoter for the immediately preceding three financial years and where annual report is not available then the audited profit and loss account, balance sheet, cash flow statement and the auditor's report of the promoter for immediately preceding three financial years and in case of newly incorporated or registered entity, such information shall be disclosed for the parent entity. 22/02/2023 16:04:59
The annual report including audited profit and loss account, balance sheet, cash flow statement, directors report and auditor's report of the promoter for the immediately preceding three financial years and where annual report is not available then the audited profit and loss account, balance sheet, cash flow statement and the auditor's report of the promoter for immediately preceding three financial years and in case of newly incorporated or registered entity, such information shall be disclosed for the parent entity. 22/02/2023 16:05:25
The annual report including audited profit and loss account, balance sheet, cash flow statement, directors report and auditor's report of the promoter for the immediately preceding three financial years and where annual report is not available then the audited profit and loss account, balance sheet, cash flow statement and the auditor's report of the promoter for immediately preceding three financial years and in case of newly incorporated or registered entity, such information shall be disclosed for the parent entity. 22/02/2023 16:10:03
ALLOTMENT DETAILS
Proforma of Agreement for Sale (As per Annexure A) Note - Promoter is directed to stick on original clauses of Annexure A. No alterations/additions/omissions are allowed in words/sentences/clauses. 17/03/2023 11:52:22
Proforma of Allotment Letter (As per the Authority order No. K-RERA/T1/1657/2024 dated 26/11/2024) 09/11/2022 13:16:50
ARCHITECT,ENGINEER & CA Certificates
Architect's Certificate in Form No 2 06/07/2024 12:31:07
Architect's Certificate in Form No 2 07/10/2024 10:02:13
Architect's Certificate in Form No 2 02/01/2025 17:43:20
Architect's Certificate in Form No 2 04/04/2025 15:20:54
Chartered Accountant's Certificate in Form No 4 (in letter head) 04/07/2023 16:18:49
Chartered Accountant's Certificate in Form No 4 (in letter head) 04/07/2023 16:20:10
Chartered Accountant's Certificate in Form No 4 (in letter head) 03/11/2023 15:57:32
Chartered Accountant's Certificate in Form No 4 (in letter head) 03/11/2023 15:57:59
Chartered Accountant's Certificate in Form No 4 (in letter head) 17/01/2024 13:16:54
Chartered Accountant's Certificate in Form No 4 (in letter head) 06/06/2024 16:00:55
Chartered Accountant's Certificate in Form No 4 (in letter head) 05/07/2024 14:40:47
Chartered Accountant's Certificate in Form No 4 (in letter head) 05/07/2024 14:40:50
Chartered Accountant's Certificate in Form No 4 (in letter head) 05/10/2024 16:40:05
Chartered Accountant's Certificate in Form No 4 (in letter head) 07/01/2025 12:08:25
Chartered Accountant's Certificate in Form No 4 (in letter head) 07/04/2025 19:29:35
Engineer's Certificate in Form No 3
NOC and other Clearance
Clearance from Airport Authority of India NA 16/02/2023 15:04:58
Clearance from Coastal Zone Management Authority NA 16/02/2023 15:05:16
Clearance from National Highways / Railways / Other Relevant Departments NA 16/02/2023 15:04:11
Concurrence / Layout Approval of LSG planning department NA 16/02/2023 15:04:25
Consent to establish (Clearance from Pollution Control Board) NA 16/02/2023 15:04:02
Environment Clearance NA 16/02/2023 15:04:39
If the project is proposed to be developed in Phases, an authenticated copy of license or land use permission, Building sanction plan or building permit for each of such phases (If applicable)
Initial NOC from Fire and Rescue department NA 16/02/2023 15:03:48
Permission from Water and sewerage department NA 16/02/2023 15:05:28
BROCHURE & OTHER DETAILS
Others Request for correcting date of completion as per Form B 11/04/2023 15:44:36
Sanction letters from Bank for construction finance
Sanction letters from bank for home loan tie-ups
PLAN OF DEVELOPMENT WORKS
Charts and the project schedule 02/03/2023 15:56:55
List and details of common amenities 02/03/2023 15:57:16
Other Plans to be executed in the proposed project
Plan for Drinking water service to be executed in the proposed project
Plan of firefighting to be executed in the proposed project
Plan of Use of renewable energy to be executed in the proposed project
BROCHURE & OTHER DETAILS
Brochure / prospectus issued in regard to this project
Completion plan (if any)
Consent to operate (Clearance from Pollution Control Board)
Declaration by the Promoter - Form No. 6
Details of Association Formed
Development certificate(for plots and villas)
Final Fire NOC
Occupancy Certificate SG17 02/08/2024 12:58:35
Occupancy Certificate SG04 20/12/2024 13:25:21
Occupancy Certificate SG03 OCCUPANCY 29/05/2025 12:43:19
Land Owner Details
Registered Joint Development Agreement 22/02/2023 16:01:45

Upload Photograph

Document Name Uploaded Document Uploaded Date
Photograph of each building 04/04/2025 16:54:08
Photograph of each building 04/04/2025 16:53:35
Photograph of each building 04/04/2025 16:53:00
Photograph of each building 04/04/2025 16:52:23
Photograph of each building 04/04/2025 16:51:40
Photograph of each building 04/04/2025 16:50:27
Photograph of each building 04/04/2025 16:49:33
Photograph of each building 04/04/2025 16:48:01
Photograph of each floor 03/01/2025 13:23:12
Photograph of each floor 03/01/2025 13:22:40
Photograph of each floor 03/01/2025 13:22:07
Photograph of each floor 03/01/2025 13:21:24
Photograph of each floor 03/01/2025 13:21:04
Photograph of each floor 03/01/2025 13:19:33
Photograph of each floor 03/01/2025 13:13:21
Photograph of each building 05/10/2024 16:46:06
Photograph of each building 05/10/2024 16:45:54
Photograph of each building 05/10/2024 16:45:28
Photograph of each building 05/10/2024 16:45:17
Photograph of each building 05/10/2024 16:45:06

Litigations Related to the Project