Sr.No. |
Building Name
|
Proposed Date of Completion (As committed to allottees)
|
Number of Basements
|
Number of Podiums
|
Number of Slab of Super Structure
|
Number of Stilts
|
Number of Open Parking
|
Number of Closed Parking
|
1 |
TREESA GARDENS VILLA 1
|
01/03/2023
|
0
|
0
|
2
|
0 |
0 |
1 |
|
|
Apartments/Villas Type Details
Sr.No.
|
Apartment/Villa Type
|
Carpet Area
|
Area of exclusive veranda
|
Area of exclusive balcony
|
Area of exclusive open terrace
|
Share of common area
|
Area of external wall
|
Total area
|
Proposed number of apartments
|
Number of apartments Booked /Sold /Allotted
|
Current value
|
Last Quarter value
|
1 |
Bangalow / Villas |
191.82 |
0 |
13.58 |
0 |
0 |
19.95 |
238.46 |
1 |
|
|
|
|
|
Parking space for Sale Details
Sr.No.
|
Parking Type
|
No. of Garages/ Covered Parking
|
Area (in Sqmts)
|
No. of Garages/ Covered Parking booked
|
Current value
|
Last Quarter value
|
1 |
Residential |
1 |
19.94 |
1 |
NA |
|
|
|
Task/Activity Details
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
Current value |
Last Quarter value |
1
|
Excavation
|
|
|
2
|
Basement(s) and Plinth
|
|
|
3
|
Stilt Floor
|
|
|
4
|
Slabs of Super Structure
|
|
|
5
|
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
|
|
|
6
|
Sanitary Fittings
|
|
|
7
|
Electrical Fittings
|
|
|
8
|
Staircases, Lifts Wells
|
|
|
9
|
Overhead and Underground Water Tanks.
|
|
|
10
|
The external plumbing and external plastering
|
|
|
11
|
Completion of terraces floor each building
|
|
|
12
|
Installation of lifts, water pumps etc
|
|
|
13
|
Fire Fighting Fittings and Equipment
|
|
|
14
|
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc
|
|
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Building Name
|
Proposed Date of Completion (As committed to allottees)
|
Number of Basements
|
Number of Podiums
|
Number of Slab of Super Structure
|
Number of Stilts
|
Number of Open Parking
|
Number of Closed Parking
|
2 |
TREESA GARDENS VILLA 5
|
01/03/2023
|
0
|
0
|
2
|
0 |
0 |
1 |
|
|
Apartments/Villas Type Details
Sr.No.
|
Apartment/Villa Type
|
Carpet Area
|
Area of exclusive veranda
|
Area of exclusive balcony
|
Area of exclusive open terrace
|
Share of common area
|
Area of external wall
|
Total area
|
Proposed number of apartments
|
Number of apartments Booked /Sold /Allotted
|
Current value
|
Last Quarter value
|
1 |
Bangalow / Villas |
140.86 |
0 |
7.76 |
0 |
0 |
17.18 |
177.44 |
1 |
|
|
|
|
|
Parking space for Sale Details
Sr.No.
|
Parking Type
|
No. of Garages/ Covered Parking
|
Area (in Sqmts)
|
No. of Garages/ Covered Parking booked
|
Current value
|
Last Quarter value
|
1 |
Residential |
1 |
14.51 |
1 |
NA |
|
|
|
Task/Activity Details
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
Current value |
Last Quarter value |
1
|
Excavation
|
|
|
2
|
Basement(s) and Plinth
|
|
|
3
|
Stilt Floor
|
|
|
4
|
Slabs of Super Structure
|
|
|
5
|
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
|
|
|
6
|
Sanitary Fittings
|
|
|
7
|
Electrical Fittings
|
|
|
8
|
Staircases, Lifts Wells
|
|
|
9
|
Overhead and Underground Water Tanks.
|
|
|
10
|
The external plumbing and external plastering
|
|
|
11
|
Completion of terraces floor each building
|
|
|
12
|
Installation of lifts, water pumps etc
|
|
|
13
|
Fire Fighting Fittings and Equipment
|
|
|
14
|
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc
|
|
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Building Name
|
Proposed Date of Completion (As committed to allottees)
|
Number of Basements
|
Number of Podiums
|
Number of Slab of Super Structure
|
Number of Stilts
|
Number of Open Parking
|
Number of Closed Parking
|
3 |
TREESA GARDENS VILLA 6
|
01/03/2023
|
0
|
0
|
2
|
0 |
0 |
1 |
|
|
Apartments/Villas Type Details
Sr.No.
|
Apartment/Villa Type
|
Carpet Area
|
Area of exclusive veranda
|
Area of exclusive balcony
|
Area of exclusive open terrace
|
Share of common area
|
Area of external wall
|
Total area
|
Proposed number of apartments
|
Number of apartments Booked /Sold /Allotted
|
Current value
|
Last Quarter value
|
1 |
Bangalow / Villas |
130.33 |
0 |
7.76 |
0 |
0 |
17.18 |
177.44 |
1 |
|
|
|
|
|
Parking space for Sale Details
Sr.No.
|
Parking Type
|
No. of Garages/ Covered Parking
|
Area (in Sqmts)
|
No. of Garages/ Covered Parking booked
|
Current value
|
Last Quarter value
|
1 |
Residential |
1 |
14.51 |
1 |
NA |
|
|
|
Task/Activity Details
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
Current value |
Last Quarter value |
1
|
Excavation
|
|
|
2
|
Basement(s) and Plinth
|
|
|
3
|
Stilt Floor
|
|
|
4
|
Slabs of Super Structure
|
|
|
5
|
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
|
|
|
6
|
Sanitary Fittings
|
|
|
7
|
Electrical Fittings
|
|
|
8
|
Staircases, Lifts Wells
|
|
|
9
|
Overhead and Underground Water Tanks.
|
|
|
10
|
The external plumbing and external plastering
|
|
|
11
|
Completion of terraces floor each building
|
|
|
12
|
Installation of lifts, water pumps etc
|
|
|
13
|
Fire Fighting Fittings and Equipment
|
|
|
14
|
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc
|
|
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Building Name
|
Proposed Date of Completion (As committed to allottees)
|
Number of Basements
|
Number of Podiums
|
Number of Slab of Super Structure
|
Number of Stilts
|
Number of Open Parking
|
Number of Closed Parking
|
4 |
TREESA GARDENS VILLA 10
|
01/03/2023
|
0
|
0
|
2
|
0 |
0 |
1 |
|
|
Apartments/Villas Type Details
Sr.No.
|
Apartment/Villa Type
|
Carpet Area
|
Area of exclusive veranda
|
Area of exclusive balcony
|
Area of exclusive open terrace
|
Share of common area
|
Area of external wall
|
Total area
|
Proposed number of apartments
|
Number of apartments Booked /Sold /Allotted
|
Current value
|
Last Quarter value
|
1 |
Bangalow / Villas |
140.86 |
0 |
7.76 |
0 |
0 |
17.18 |
177.49 |
1 |
|
|
|
|
|
Parking space for Sale Details
Sr.No.
|
Parking Type
|
No. of Garages/ Covered Parking
|
Area (in Sqmts)
|
No. of Garages/ Covered Parking booked
|
Current value
|
Last Quarter value
|
1 |
Residential |
1 |
14.51 |
1 |
NA |
|
|
|
Task/Activity Details
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
Current value |
Last Quarter value |
1
|
Excavation
|
|
|
2
|
Basement(s) and Plinth
|
|
|
3
|
Stilt Floor
|
|
|
4
|
Slabs of Super Structure
|
|
|
5
|
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
|
|
|
6
|
Sanitary Fittings
|
|
|
7
|
Electrical Fittings
|
|
|
8
|
Staircases, Lifts Wells
|
|
|
9
|
Overhead and Underground Water Tanks.
|
|
|
10
|
The external plumbing and external plastering
|
|
|
11
|
Completion of terraces floor each building
|
|
|
12
|
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc
|
|
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Building Name
|
Proposed Date of Completion (As committed to allottees)
|
Number of Basements
|
Number of Podiums
|
Number of Slab of Super Structure
|
Number of Stilts
|
Number of Open Parking
|
Number of Closed Parking
|
5 |
TREESA GARDENS VILLA 11
|
01/03/2023
|
0
|
0
|
2
|
0 |
0 |
1 |
|
|
Apartments/Villas Type Details
Sr.No.
|
Apartment/Villa Type
|
Carpet Area
|
Area of exclusive veranda
|
Area of exclusive balcony
|
Area of exclusive open terrace
|
Share of common area
|
Area of external wall
|
Total area
|
Proposed number of apartments
|
Number of apartments Booked /Sold /Allotted
|
Current value
|
Last Quarter value
|
1 |
Bangalow / Villas |
140.46 |
0 |
7.76 |
0 |
0 |
17.18 |
177.44 |
1 |
|
|
|
|
|
Parking space for Sale Details
Sr.No.
|
Parking Type
|
No. of Garages/ Covered Parking
|
Area (in Sqmts)
|
No. of Garages/ Covered Parking booked
|
Current value
|
Last Quarter value
|
1 |
Residential |
1 |
14.51 |
1 |
NA |
|
|
|
Task/Activity Details
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
Current value |
Last Quarter value |
1
|
Excavation
|
|
|
2
|
Basement(s) and Plinth
|
|
|
3
|
Stilt Floor
|
|
|
4
|
Slabs of Super Structure
|
|
|
5
|
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
|
|
|
6
|
Sanitary Fittings
|
|
|
7
|
Electrical Fittings
|
|
|
8
|
Staircases, Lifts Wells
|
|
|
9
|
Overhead and Underground Water Tanks.
|
|
|
10
|
The external plumbing and external plastering
|
|
|
11
|
Completion of terraces floor each building
|
|
|
12
|
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc
|
|
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Building Name
|
Proposed Date of Completion (As committed to allottees)
|
Number of Basements
|
Number of Podiums
|
Number of Slab of Super Structure
|
Number of Stilts
|
Number of Open Parking
|
Number of Closed Parking
|
6 |
TREESA GARDENS VILLA 12
|
01/03/2023
|
0
|
0
|
2
|
0 |
0 |
1 |
|
|
Apartments/Villas Type Details
Sr.No.
|
Apartment/Villa Type
|
Carpet Area
|
Area of exclusive veranda
|
Area of exclusive balcony
|
Area of exclusive open terrace
|
Share of common area
|
Area of external wall
|
Total area
|
Proposed number of apartments
|
Number of apartments Booked /Sold /Allotted
|
Current value
|
Last Quarter value
|
1 |
Bangalow / Villas |
160.69 |
0 |
20.89 |
0 |
0 |
18.41 |
221.69 |
1 |
|
|
|
|
|
Parking space for Sale Details
Sr.No.
|
Parking Type
|
No. of Garages/ Covered Parking
|
Area (in Sqmts)
|
No. of Garages/ Covered Parking booked
|
Current value
|
Last Quarter value
|
1 |
Residential |
1 |
20.89 |
1 |
NA |
|
|
|
Task/Activity Details
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
Current value |
Last Quarter value |
1
|
Excavation
|
|
|
2
|
Basement(s) and Plinth
|
|
|
3
|
Stilt Floor
|
|
|
4
|
Slabs of Super Structure
|
|
|
5
|
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
|
|
|
6
|
Sanitary Fittings
|
|
|
7
|
Electrical Fittings
|
|
|
8
|
Staircases, Lifts Wells
|
|
|
9
|
Overhead and Underground Water Tanks.
|
|
|
10
|
The external plumbing and external plastering
|
|
|
11
|
Completion of terraces floor each building
|
|
|
12
|
Installation of lifts, water pumps etc
|
|
|
13
|
Fire Fighting Fittings and Equipment
|
|
|
14
|
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc
|
|
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Building Name
|
Proposed Date of Completion (As committed to allottees)
|
Number of Basements
|
Number of Podiums
|
Number of Slab of Super Structure
|
Number of Stilts
|
Number of Open Parking
|
Number of Closed Parking
|
7 |
Villa 2
|
01/03/2023
|
0
|
0
|
2
|
0 |
0 |
1 |
|
|
Apartments/Villas Type Details
Sr.No.
|
Apartment/Villa Type
|
Carpet Area
|
Area of exclusive veranda
|
Area of exclusive balcony
|
Area of exclusive open terrace
|
Share of common area
|
Area of external wall
|
Total area
|
Proposed number of apartments
|
Number of apartments Booked /Sold /Allotted
|
Current value
|
Last Quarter value
|
1 |
Bangalow / Villas |
202.07 |
0 |
20.07 |
0 |
0 |
22.66 |
249.78 |
1 |
|
|
|
|
|
Parking space for Sale Details
Sr.No.
|
Parking Type
|
No. of Garages/ Covered Parking
|
Area (in Sqmts)
|
No. of Garages/ Covered Parking booked
|
Current value
|
Last Quarter value
|
1 |
Residential |
1 |
20.96 |
0 |
NA |
|
|
|
Task/Activity Details
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
Current value |
Last Quarter value |
1
|
Excavation
|
|
|
2
|
Basement(s) and Plinth
|
|
|
3
|
Stilt Floor
|
|
|
4
|
Slabs of Super Structure
|
|
|
5
|
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
|
|
|
6
|
Sanitary Fittings
|
|
|
7
|
Electrical Fittings
|
|
|
8
|
Staircases, Lifts Wells
|
|
|
9
|
Overhead and Underground Water Tanks.
|
|
|
10
|
The external plumbing and external plastering
|
|
|
11
|
Completion of terraces floor each building
|
|
|
12
|
Installation of lifts, water pumps etc
|
|
|
13
|
Fire Fighting Fittings and Equipment
|
|
|
14
|
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc
|
|
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Building Name
|
Proposed Date of Completion (As committed to allottees)
|
Number of Basements
|
Number of Podiums
|
Number of Slab of Super Structure
|
Number of Stilts
|
Number of Open Parking
|
Number of Closed Parking
|
8 |
Villa 3
|
01/03/2023
|
0
|
0
|
2
|
0 |
0 |
1 |
|
|
Apartments/Villas Type Details
Sr.No.
|
Apartment/Villa Type
|
Carpet Area
|
Area of exclusive veranda
|
Area of exclusive balcony
|
Area of exclusive open terrace
|
Share of common area
|
Area of external wall
|
Total area
|
Proposed number of apartments
|
Number of apartments Booked /Sold /Allotted
|
Current value
|
Last Quarter value
|
1 |
Bangalow / Villas |
191.35 |
0 |
19.50 |
0 |
0 |
21.50 |
236.41 |
1 |
|
|
|
|
|
Parking space for Sale Details
Sr.No.
|
Parking Type
|
No. of Garages/ Covered Parking
|
Area (in Sqmts)
|
No. of Garages/ Covered Parking booked
|
Current value
|
Last Quarter value
|
1 |
Residential |
1 |
18.78 |
0 |
NA |
|
|
|
Task/Activity Details
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
Current value |
Last Quarter value |
1
|
Excavation
|
|
|
2
|
Basement(s) and Plinth
|
|
|
3
|
Stilt Floor
|
|
|
4
|
Slabs of Super Structure
|
|
|
5
|
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
|
|
|
6
|
Sanitary Fittings
|
|
|
7
|
Electrical Fittings
|
|
|
8
|
Staircases, Lifts Wells
|
|
|
9
|
Overhead and Underground Water Tanks.
|
|
|
10
|
The external plumbing and external plastering
|
|
|
11
|
Completion of terraces floor each building
|
|
|
12
|
Installation of lifts, water pumps etc
|
|
|
13
|
Fire Fighting Fittings and Equipment
|
|
|
14
|
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc
|
|
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Building Name
|
Proposed Date of Completion (As committed to allottees)
|
Number of Basements
|
Number of Podiums
|
Number of Slab of Super Structure
|
Number of Stilts
|
Number of Open Parking
|
Number of Closed Parking
|
9 |
Villa 4
|
01/03/2023
|
0
|
0
|
2
|
0 |
0 |
1 |
|
|
Apartments/Villas Type Details
Sr.No.
|
Apartment/Villa Type
|
Carpet Area
|
Area of exclusive veranda
|
Area of exclusive balcony
|
Area of exclusive open terrace
|
Share of common area
|
Area of external wall
|
Total area
|
Proposed number of apartments
|
Number of apartments Booked /Sold /Allotted
|
Current value
|
Last Quarter value
|
1 |
Bangalow / Villas |
142.35 |
0 |
8.50 |
0 |
0 |
19.30 |
188.64 |
1 |
|
|
|
|
|
Parking space for Sale Details
Sr.No.
|
Parking Type
|
No. of Garages/ Covered Parking
|
Area (in Sqmts)
|
No. of Garages/ Covered Parking booked
|
Current value
|
Last Quarter value
|
1 |
Residential |
1 |
14.52 |
0 |
NA |
|
|
|
Task/Activity Details
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
Current value |
Last Quarter value |
1
|
Excavation
|
|
|
2
|
Basement(s) and Plinth
|
|
|
3
|
Stilt Floor
|
|
|
4
|
Slabs of Super Structure
|
|
|
5
|
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
|
|
|
6
|
Sanitary Fittings
|
|
|
7
|
Electrical Fittings
|
|
|
8
|
Staircases, Lifts Wells
|
|
|
9
|
Overhead and Underground Water Tanks.
|
|
|
10
|
The external plumbing and external plastering
|
|
|
11
|
Completion of terraces floor each building
|
|
|
12
|
Installation of lifts, water pumps etc
|
|
|
13
|
Fire Fighting Fittings and Equipment
|
|
|
14
|
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc
|
|
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Building Name
|
Proposed Date of Completion (As committed to allottees)
|
Number of Basements
|
Number of Podiums
|
Number of Slab of Super Structure
|
Number of Stilts
|
Number of Open Parking
|
Number of Closed Parking
|
10 |
Villa 7
|
01/03/2023
|
0
|
0
|
2
|
0 |
0 |
1 |
|
|
Apartments/Villas Type Details
Sr.No.
|
Apartment/Villa Type
|
Carpet Area
|
Area of exclusive veranda
|
Area of exclusive balcony
|
Area of exclusive open terrace
|
Share of common area
|
Area of external wall
|
Total area
|
Proposed number of apartments
|
Number of apartments Booked /Sold /Allotted
|
Current value
|
Last Quarter value
|
1 |
Bangalow / Villas |
144.50 |
0 |
7.76 |
0 |
0 |
17.18 |
201.14 |
1 |
|
|
|
|
|
Parking space for Sale Details
Sr.No.
|
Parking Type
|
No. of Garages/ Covered Parking
|
Area (in Sqmts)
|
No. of Garages/ Covered Parking booked
|
Current value
|
Last Quarter value
|
1 |
Residential |
1 |
16.70 |
0 |
NA |
|
|
|
Task/Activity Details
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
Current value |
Last Quarter value |
1
|
Excavation
|
|
|
2
|
Basement(s) and Plinth
|
|
|
3
|
Stilt Floor
|
|
|
4
|
Slabs of Super Structure
|
|
|
5
|
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
|
|
|
6
|
Sanitary Fittings
|
|
|
7
|
Electrical Fittings
|
|
|
8
|
Staircases, Lifts Wells
|
|
|
9
|
Overhead and Underground Water Tanks.
|
|
|
10
|
The external plumbing and external plastering
|
|
|
11
|
Completion of terraces floor each building
|
|
|
12
|
Installation of lifts, water pumps etc
|
|
|
13
|
Fire Fighting Fittings and Equipment
|
|
|
14
|
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc
|
|
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Building Name
|
Proposed Date of Completion (As committed to allottees)
|
Number of Basements
|
Number of Podiums
|
Number of Slab of Super Structure
|
Number of Stilts
|
Number of Open Parking
|
Number of Closed Parking
|
11 |
Villa 8
|
01/03/2023
|
0
|
0
|
2
|
0 |
0 |
1 |
|
|
Apartments/Villas Type Details
Sr.No.
|
Apartment/Villa Type
|
Carpet Area
|
Area of exclusive veranda
|
Area of exclusive balcony
|
Area of exclusive open terrace
|
Share of common area
|
Area of external wall
|
Total area
|
Proposed number of apartments
|
Number of apartments Booked /Sold /Allotted
|
Current value
|
Last Quarter value
|
1 |
Bangalow / Villas |
140.86 |
0 |
7.76 |
0 |
0 |
17.18 |
177.44 |
1 |
|
|
|
|
|
Parking space for Sale Details
Sr.No.
|
Parking Type
|
No. of Garages/ Covered Parking
|
Area (in Sqmts)
|
No. of Garages/ Covered Parking booked
|
Current value
|
Last Quarter value
|
1 |
Residential |
1 |
14.51 |
0 |
NA |
|
|
|
Task/Activity Details
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
Current value |
Last Quarter value |
1
|
Excavation
|
|
|
2
|
Basement(s) and Plinth
|
|
|
3
|
Stilt Floor
|
|
|
4
|
Slabs of Super Structure
|
|
|
5
|
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
|
|
|
6
|
Sanitary Fittings
|
|
|
7
|
Electrical Fittings
|
|
|
8
|
Staircases, Lifts Wells
|
|
|
9
|
Overhead and Underground Water Tanks.
|
|
|
10
|
The external plumbing and external plastering
|
|
|
11
|
Completion of terraces floor each building
|
|
|
12
|
Installation of lifts, water pumps etc
|
|
|
13
|
Fire Fighting Fittings and Equipment
|
|
|
14
|
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc
|
|
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Building Name
|
Proposed Date of Completion (As committed to allottees)
|
Number of Basements
|
Number of Podiums
|
Number of Slab of Super Structure
|
Number of Stilts
|
Number of Open Parking
|
Number of Closed Parking
|
12 |
Villa 9
|
01/03/2023
|
0
|
0
|
2
|
0 |
0 |
1 |
|
|
Apartments/Villas Type Details
Sr.No.
|
Apartment/Villa Type
|
Carpet Area
|
Area of exclusive veranda
|
Area of exclusive balcony
|
Area of exclusive open terrace
|
Share of common area
|
Area of external wall
|
Total area
|
Proposed number of apartments
|
Number of apartments Booked /Sold /Allotted
|
Current value
|
Last Quarter value
|
1 |
Bangalow / Villas |
140.86 |
0 |
7.76 |
0 |
0 |
7.76 |
177.44 |
1 |
|
|
|
|
|
Parking space for Sale Details
Sr.No.
|
Parking Type
|
No. of Garages/ Covered Parking
|
Area (in Sqmts)
|
No. of Garages/ Covered Parking booked
|
Current value
|
Last Quarter value
|
1 |
Residential |
1 |
14.51 |
0 |
NA |
|
|
|
Task/Activity Details
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
Current value |
Last Quarter value |
1
|
Excavation
|
|
|
2
|
Basement(s) and Plinth
|
|
|
3
|
Slabs of Super Structure
|
|
|
4
|
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
|
|
|
5
|
Sanitary Fittings
|
|
|
6
|
Electrical Fittings
|
|
|
7
|
Staircases, Lifts Wells
|
|
|
8
|
Overhead and Underground Water Tanks.
|
|
|
9
|
The external plumbing and external plastering
|
|
|
10
|
Completion of terraces floor each building
|
|
|
11
|
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc
|
|
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Building Name
|
Proposed Date of Completion (As committed to allottees)
|
Number of Basements
|
Number of Podiums
|
Number of Slab of Super Structure
|
Number of Stilts
|
Number of Open Parking
|
Number of Closed Parking
|
13 |
Villa 13
|
01/03/2023
|
0
|
0
|
2
|
0 |
0 |
1 |
|
|
Apartments/Villas Type Details
Sr.No.
|
Apartment/Villa Type
|
Carpet Area
|
Area of exclusive veranda
|
Area of exclusive balcony
|
Area of exclusive open terrace
|
Share of common area
|
Area of external wall
|
Total area
|
Proposed number of apartments
|
Number of apartments Booked /Sold /Allotted
|
Current value
|
Last Quarter value
|
1 |
Bangalow / Villas |
172.49 |
0 |
20.80 |
0 |
20.80 |
18 |
239.09 |
1 |
|
|
|
|
|
Parking space for Sale Details
Sr.No.
|
Parking Type
|
No. of Garages/ Covered Parking
|
Area (in Sqmts)
|
No. of Garages/ Covered Parking booked
|
Current value
|
Last Quarter value
|
1 |
Residential |
1 |
19.80 |
0 |
NA |
|
|
|
Task/Activity Details
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
Current value |
Last Quarter value |
1
|
Excavation
|
|
|
2
|
Basement(s) and Plinth
|
|
|
3
|
Stilt Floor
|
|
|
4
|
Slabs of Super Structure
|
|
|
5
|
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
|
|
|
6
|
Sanitary Fittings
|
|
|
7
|
Electrical Fittings
|
|
|
8
|
Staircases, Lifts Wells
|
|
|
9
|
Overhead and Underground Water Tanks.
|
|
|
10
|
The external plumbing and external plastering
|
|
|
11
|
Completion of terraces floor each building
|
|
|
12
|
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc
|
|
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Building Name
|
Proposed Date of Completion (As committed to allottees)
|
Number of Basements
|
Number of Podiums
|
Number of Slab of Super Structure
|
Number of Stilts
|
Number of Open Parking
|
Number of Closed Parking
|
14 |
Villa 14
|
01/03/2023
|
0
|
0
|
2
|
0 |
0 |
1 |
|
|
Apartments/Villas Type Details
Sr.No.
|
Apartment/Villa Type
|
Carpet Area
|
Area of exclusive veranda
|
Area of exclusive balcony
|
Area of exclusive open terrace
|
Share of common area
|
Area of external wall
|
Total area
|
Proposed number of apartments
|
Number of apartments Booked /Sold /Allotted
|
Current value
|
Last Quarter value
|
1 |
Bangalow / Villas |
145.85 |
0 |
8.50 |
0 |
0 |
18 |
196.82 |
1 |
|
|
|
|
|
Parking space for Sale Details
Sr.No.
|
Parking Type
|
No. of Garages/ Covered Parking
|
Area (in Sqmts)
|
No. of Garages/ Covered Parking booked
|
Current value
|
Last Quarter value
|
1 |
Residential |
1 |
13.48 |
0 |
NA |
|
|
|
Task/Activity Details
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
Current value |
Last Quarter value |
1
|
Excavation
|
|
|
2
|
Basement(s) and Plinth
|
|
|
3
|
Stilt Floor
|
|
|
4
|
Slabs of Super Structure
|
|
|
5
|
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
|
|
|
6
|
Sanitary Fittings
|
|
|
7
|
Electrical Fittings
|
|
|
8
|
Staircases, Lifts Wells
|
|
|
9
|
Overhead and Underground Water Tanks.
|
|
|
10
|
The external plumbing and external plastering
|
|
|
11
|
Completion of terraces floor each building
|
|
|
12
|
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc
|
|
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Building Name
|
Proposed Date of Completion (As committed to allottees)
|
Number of Basements
|
Number of Podiums
|
Number of Slab of Super Structure
|
Number of Stilts
|
Number of Open Parking
|
Number of Closed Parking
|
15 |
Villa 15
|
01/03/2023
|
0
|
0
|
2
|
0 |
0 |
1 |
|
|
Apartments/Villas Type Details
Sr.No.
|
Apartment/Villa Type
|
Carpet Area
|
Area of exclusive veranda
|
Area of exclusive balcony
|
Area of exclusive open terrace
|
Share of common area
|
Area of external wall
|
Total area
|
Proposed number of apartments
|
Number of apartments Booked /Sold /Allotted
|
Current value
|
Last Quarter value
|
1 |
Bangalow / Villas |
174.73 |
0 |
14.78 |
0 |
0 |
18.81 |
221.69 |
1 |
|
|
|
|
|
Parking space for Sale Details
Sr.No.
|
Parking Type
|
No. of Garages/ Covered Parking
|
Area (in Sqmts)
|
No. of Garages/ Covered Parking booked
|
Current value
|
Last Quarter value
|
1 |
Residential |
1 |
20.89 |
0 |
NA |
|
|
|
Task/Activity Details
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
Current value |
Last Quarter value |
1
|
Excavation
|
|
|
2
|
Basement(s) and Plinth
|
|
|
3
|
Stilt Floor
|
|
|
4
|
Slabs of Super Structure
|
|
|
5
|
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
|
|
|
6
|
Sanitary Fittings
|
|
|
7
|
Electrical Fittings
|
|
|
8
|
Staircases, Lifts Wells
|
|
|
9
|
Overhead and Underground Water Tanks.
|
|
|
10
|
The external plumbing and external plastering
|
|
|
11
|
Completion of terraces floor each building
|
|
|
12
|
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc
|
|
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|