KeralaRERA Application

General Information

T1/OL/009/2021
19/03/2021


Promoter's Information - Other Than Individual


Company
Sree Dhanya Homes Pvt ltd
Yes
No

Registered address of the Promoter

Sree Dhanya Homes Pvt Ltd, 31/747
Sasthamangalam PO
KERALA
Thiruvananthapuram
THIRUVANANTHAPRUAM
695010

Address for official communication

Sree Dhanya Homes Pvt Ltd, 31/747
Sasthamangalam PO
Sasthamangalm
Opp KPCC OFFICE
KERALA
Thiruvananthapuram
THIRUVANANTHAPRUAM
THIRUVANANTHAPURAM
695010
Member Name Designation Photo
Dhanya Babu Managing Director View Photo
Dhanya Babu Authorized Signatory View Photo
SRUTHY LALAN VELIYIL Director View Photo

Promoter's Past Experience Details

Sr No. Project Name Project Address Land Area (In Sq mtrs) Details of payments pending Current status of the project Details of cases/ litigations related to the project Date of commencement Proposed date of completion Actual completion date Remarks (If any) Other relevant experience
1 La Poshe Vazhuthacaud 3.99 0 completed 0 14/03/2016 01/12/2019 NA NA NA
2 LAKE WOODS AKKULAM,TRIVANDRUM 4048 50000000 OCCUPANCY RECEIVED NA 01/04/2016 27/12/2018 05/12/2018 NA NA

Promoter's Track Record

40
0
10
85000
2
14000

Project Information

On-Going Project
vantage point
Others
15/06/2018
01/02/2024
Yes
Yes

Land Details

2793
1
13725.15
8615
11
93
0

Location Details of the Project Area

2937/A1
34719
KERALA
Thiruvananthapuram
THIRUVANANTHAPRUAM
VANCHIYOOR
BAKERY JUNCTION
695654
PWD Road
Property of Johnson. D Sahayam
Corporation Road
Santhi wood Land Property

Mortgages

SBI
SBI SME BRANCH,ANDOOR BUILDING,GENERAL HOSPITAL ROAD, VANCHIYOOR PO, TRIVANDRUM 695035

Building Permit Details

Building Permit Number Dated Type Date of Expiry Issued by Name of the Local body/ LSGI
22/05/2018 21/05/2021 Secretary Thiruvananthapuram Corporation

Development Permit Details

Development Permit Number Dated Type Date of Expiry Issued by Name of the Local body/ LSGI
E13/E14/BA/153482/16 22/05/2018 New 21/05/2021 Secretary Thiruvananthapuram Corporation

Co-promoter/ Land owner details

Land owner Name Type of Land Owner PAN Number Type of Agreement/ Arrangement Office Number (With area code) Other Details
Cherian Paul Individual AEZPP6250Q RevenueShare 04712723682

Building Details

Sr.No. Building Name Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 VANTAGE POINT 1 2 13 1 0 82

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
1 1BHK 46.11 0 0 0 14.74 0.00 60.85 82 43

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 Stilt Floor 100
4 X number of Slabs of Super Structure 100
5 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
6 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
7 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
8 The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing 10
9

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby(s), plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate

10
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
11 Overall Percentage of Completion of the work done For the entire Building /Wing 66.5

Common Areas and Facilities

Project Details

Name Proposed Number Progerss of work done (In %)
Number of Garages/ Covered Parking (In Numbers) (Common Area) 82 100

Development Work

Common areas And Facilities, Amenities Proposed Percentage of completion Details
Internal Roads & Footpaths : YES 75 Formation in Progress
Visitors Parking : YES 75 Formation in Progress
Water conservation, Rain water harvesting : YES 10 Earth Work in Progress
Energy Management : YES 75 Wiring in Progress
Fire protection and Fire safety requirements : YES 10 Tender in Process
Electrical meter room, Sub-station, Receiving station : YES 40 Masonry in Progress
Aggregate area of recreational open space : YES 40 Formation in Progress
Open parking : YES 40 Formation In Progress
Water supply : YES 40 Inside apartment plumbing work in progress
Sewerage (Chamber, Lines, Septic tank, STP) : YES 40 Inside apartment sewerage work in progress
Storm water drains : YES 40 Inside apartment storm water work in progress
Landscaping & Tree planting : YES 10 Formation in Progress
Street lighting : YES 10 In progress
Community buildings : NO 0 NA
Treatment and disposal of sewage and sullage water : YES 10 In Progress
Solid waste management and disposal : YES 10 In Progress
Public health services : NO 0 NA
Swimming Pool : YES 75 StructureCompleted
Health Club : YES 75 MasonryCompleted
AV Board Room : YES 75 Masonarycompleted
Roof Top Cafeteria : YES 50 Workinprogress
Business Hub : YES 75 Masonarycompleted
Association Hall : YES 50 workinprogress

Professional Information

Professional Name RERA Certificate No. Professional Type
JAYAKRISHNAN NA Architect
SYNO MATHEW JOHN NA Engineer
RAVI CHELLAPAN NA Chartered Accountant

Uploaded Documents

Document Name Uploaded Document Remarks
Copy of PAN card
The annual report including audited profit and loss account, balance sheet, cash flow statement, directors report and auditor's report of the promoter for the immedietly preceding three financial years and where annual report is not available then the audited profit and loss account, balance sheet, cash flow statement and the auditor's report of the promoter for immedietly preceding three financial years and in case of newly incorporated or registered entity, such information shall be disclosed for the parent entity.
Consent to establish & operate (Clearance from Pollution Control Board)
Environment Clearance
NOC from Fire and Rescue department
Permission from Water and sewerage department
Clearance from Airport Authority of India
Clearance from National Highways / Railways / Other Relevant Departments
Clearance from Coastal Zone Management Authority
Site Plan / Site Map
Layout approval plan
Concurrence of Town and Country planning department
If the project is proposed to be developed in Phases, an authenticated copy of license or land use permission, Building sanction plan or building permit for each of such phases
Copy of Building Permit
Copy of Development Permit
Copy of Sanctioned Plans
Performa of Allotment Letter
Performa of Agreement for Sale (As per Annexure A)
Performa of Conveyance Deed
Copy of Title Deed
Copy of Title Deed
Land title search report
Copy of latest Land Tax Receipt
Details of Encumbrance
Occupancy Certificate/ Completion Certificate/ development certificate
The Plan of development works to be executed in the proposed project
Brochure / prospectus issued in regard to this project
Sanction letters from Bank for construction finance
Sanction letters form bank for home loan tie-ups
Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points
Detailed technical specifications to be adopted in the project
Others

Upload Photograph

Document Name Uploaded Document
Photograph of each building

Litigations Related to the Project

Name Of The Court Type of Case Petition Type Case Number Year Whether any Preventive/ Injunction/ Interim Order is Passed Present Status Case Related Documents
NA Other - NO CASE Other - NO NA 2019 No NA
NA