General Information

K-RERA/PRJ/TVM/066/2022
Cordial i-Nest
Cordial Properties India Pvt Ltd
Villas (Plots & Buildings)
06/04/2024
Click Here

Quarterly updated values

Project Information

Cordial i-Nest
Villas (Plots & Buildings)
18/04/2022
31/12/2025
No
No

Land Details

3289
14
2670.21
2670.21
0
14
0

Location Details of the Project Area

S-1423/1 R 267/14, S-1424/2 R-267/13
17659
KERALA
Thiruvananthapuram
THIRUVANANTHAPRUAM
VEILOOR
Edavilakom
Mangalapuram
695302
Panchayat Road
Footpath and Property of Velayudhan Chettiyar
Properties of Dhanapalan and Abdul Salim
Property of Rajasekharan

Mortgages

Promoter's Information - Other Than Individual


Company
Cordial Properties India Pvt Ltd
Yes
Yes

Newly Incorporated of Registrered Entity

Cordial Foundation Pvt Ltd
Company

Registered Address of the parent entinty

T.C 9/2561
Near KPCC Office, Vellayambalam
KERALA
Thiruvananthapuram
THIRUVANANTHAPRUAM
695010

Registered address of the Promoter

TC 18/106
Muttada.P.O
Kowdiar Village
KERALA
Thiruvananthapuram
THIRUVANANTHAPRUAM
695025

Address for official communication

TC 18/106
Muttada.P.O
Kowdiar Village
KERALA
Thiruvananthapuram
THIRUVANANTHAPRUAM
695025
Member Name Designation Photo
Karthik K Director View Photo
Sushama Unnithan Director View Photo
N Kochaniyan Unnithan Authorized Signatory View Photo
N Kochaniyan Unnithan Managing Director View Photo

Land owner details

Promoter's Past Experience Details

Sr No. Project Name RERA registration number Project Address Land Area (In Sq mtrs) Details of payments pending Current status of the project Details of cases/ litigations related to the project Date of commencement Proposed date of completion Actual completion date Remarks (If any) Other relevant experience
1 Cordial Skyview Cordial Skyview, Karamana, Thiruvananthapuram, Kerala 695012 2168 31607227 Completed, OC awaited Nil 24/08/2016 30/09/2020 NA NA NA
2 Cordial Dhanuss Maruthumkuzhi, Thiruvananthapuram, Kerala 695030 1740 52123584 Completed, OC obtained Nil 16/07/2017 30/09/2020 11/11/2020 NA NA
//}

Promoter's Track Record

10
0
5
53681
1
12560

Building Permit Details

Building Permit Number Dated Type Date of Expiry Issued by Name of the Local body/ LSGI

Development Permit Details

Development Permit Number Dated Type Date of Expiry Issued by Name of the Local body/ LSGI

Building Details

Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 Plot 1 31/12/2025 0 0 2 2 0 1

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 163.96 23.86 8.30 0 15 21.66 232.78 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 1 17.61 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 Plot 2 31/12/2025 0 0 2 2 0 1

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 160.21 11.69 2.72 0 13.37 19.55 207.54 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 1 8.97 1 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 Plot 3 31/12/2025 0 0 2 2 0 1

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 160.21 11.69 2.72 0 13.37 19.55 207.54 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 1 8.97 1 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 Plot 4 31/12/2025 0 0 2 2 0 1

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 160.21 11.69 2.72 0 13.37 19.55 207.54 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 1 8.97 1 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
5 Plot 5 31/12/2025 0 0 2 2 0 1

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 162.82 14.46 3.59 0 13.86 20.39 215.12 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 1 10.86 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
6 Plot 6 31/12/2025 0 0 2 2 0 1

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 148.49 13.15 4.78 0 12.73 18.42 197.57 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 1 8.39 1 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
7 Plot 7 31/12/2025 0 0 2 2 0 1

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 139.54 16.23 3.77 0 12.22 17.94 189.70 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 1 12.57 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
8 Plot 8 31/12/2025 0 0 2 2 0 1

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 131.48 11.94 3.84 0 11.27 16.29 174.82 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 1 8.13 1 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
9 Plot 9 31/12/2025 0 0 2 2 0 1

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 146.81 11.95 5.52 0 12.64 19.21 196.13 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 1 7.89 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
10 Plot 10 31/12/2025 0 0 2 2 0 1

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 165.56 15.64 5.35 0 14.10 18.17 218.82 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 1 10.52 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
11 Plot 11 31/12/2025 0 0 2 2 0 1

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 160.21 11.69 2.72 0 13.37 19.55 207.54 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 1 8.97 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
12 Plot 12 31/12/2025 0 0 2 2 0 1

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 160.21 11.69 2.72 0 13.37 19.55 207.54 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 1 8.97 1 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
13 Plot 13 31/12/2025 0 0 2 2 0 1

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 160.21 11.69 2.72 0 13.37 19.55 207.54 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 1 8.97 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
14 Plot 14- Recreational Building 31/12/2025 0 0 3 4 2 0

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Others-Recreation 144.05 3.17 0 0 0 24.85 172.07 0

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Others-Recreation 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Common Areas and Facilities

Project Details

Name Proposed Number Progress of work done (In %)
Current value Last Quarter value
Number of Garages/ Covered Parking (In Numbers) (Common Area) 0

Development Work

Common areas And Facilities, Amenities Proposed Percentage of completion Details
Current value Last Quarter value
Open parking :
Water conservation, Rain water harvesting :
Solid waste management and disposal :
Internal Roads & Footpaths :
Aggregate area of recreational open space :
Sewerage (Chamber, Lines, Septic tank, STP) :
Community buildings :
Water supply :
Storm water drains :
Electrical meter room, Sub-station, Receiving station :
Street lighting :
Landscaping & Tree planting :

Professional Information

Professional Name RERA Certificate No. Professional Type Type of Contractor Registration Number Name of the firm Address of the firm Year of establishment Name of Promoters Associated with Key projects completed Type of Professional
Koshy K Alex NA Architect NA CA/86/9765 Vasthushilpalaya Consultncy Pvt Ltd 1st Floor, Mark Towers, Sasthamangalam, Trivandrum-10 2002 Cordial Foundation Pvt Ltd, Dr. B.R Shetty, Artech realtors, PPD Courtyard by Marriot 5 star hotel at Akkulam Trivandrum, Samrushi Thampurans Apartment at Trivandrum NA
Karthik K NA Engineer NA NA Cordial Foundation Pvt Ltd TC 9/2561, Near KPCC Office, Vellayalambalam, trivandrum-10 2018 Cordial Group Cordial Skyview, Jagathy Cordial Dhanuss, Sasthamangalam NA
M Ramesh Kumar NA Chartered Accountant NA 0107455 M Ramesh Kumar and Co Krishnageetham, VNRA167, Bhagavathy Nagar, NCC Road, Ambalamukku, Trivandrum 695005 1989 Cordial Foundation Pvt Ltd, South Park Cordial Bharathi NA

Uploaded Documents

Document Name Uploaded Document Remarks Uploaded Date
PROJECT DETAILS
Copy of Sanctioned Plans 01/04/2022 13:06:35
Copy of Valid Building Permit 01/04/2022 13:13:06
Copy of Valid Development Permit 01/04/2022 13:13:14
Detailed technical specifications to be adopted in the project 07/04/2022 17:14:14
Details of Association Formed
Layout approval plan 01/04/2022 13:15:14
Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points 07/04/2022 17:15:24
Occupancy Certificate/Development certificate
Site Plan / Site Map 01/04/2022 13:15:33
LAND DETAILS
Copy of latest Land Tax Receipt 01/04/2022 13:20:34
Copy of Title Deed 01/04/2022 13:21:07
Copy of Title Deed 01/04/2022 13:21:16
Details of Encumbrance 07/04/2022 17:15:40
Land title search report (From an advocate as specified in Rule 17) 01/04/2022 13:21:38
Proforma of Conveyance Deed / Sales Deed 01/04/2022 13:24:38
PROMOTER DETAILS
Declaration in Form B 01/04/2022 13:25:42
The annual report including audited profit and loss account, balance sheet, cash flow statement, directors report and auditor's report of the promoter for the immedietly preceding three financial years and where annual report is not available then the audited profit and loss account, balance sheet, cash flow statement and the auditor's report of the promoter for immedietly preceding three financial years and in case of newly incorporated or registered entity, such information shall be disclosed for the parent entity. 01/04/2022 13:26:54
The annual report including audited profit and loss account, balance sheet, cash flow statement, directors report and auditor's report of the promoter for the immedietly preceding three financial years and where annual report is not available then the audited profit and loss account, balance sheet, cash flow statement and the auditor's report of the promoter for immedietly preceding three financial years and in case of newly incorporated or registered entity, such information shall be disclosed for the parent entity. 01/04/2022 13:27:08
The annual report including audited profit and loss account, balance sheet, cash flow statement, directors report and auditor's report of the promoter for the immedietly preceding three financial years and where annual report is not available then the audited profit and loss account, balance sheet, cash flow statement and the auditor's report of the promoter for immedietly preceding three financial years and in case of newly incorporated or registered entity, such information shall be disclosed for the parent entity. 01/04/2022 13:27:22
The annual report including audited profit and loss account, balance sheet, cash flow statement, directors report and auditor's report of the promoter for the immedietly preceding three financial years and where annual report is not available then the audited profit and loss account, balance sheet, cash flow statement and the auditor's report of the promoter for immedietly preceding three financial years and in case of newly incorporated or registered entity, such information shall be disclosed for the parent entity. 07/04/2022 17:26:34
The annual report including audited profit and loss account, balance sheet, cash flow statement, directors report and auditor's report of the promoter for the immedietly preceding three financial years and where annual report is not available then the audited profit and loss account, balance sheet, cash flow statement and the auditor's report of the promoter for immedietly preceding three financial years and in case of newly incorporated or registered entity, such information shall be disclosed for the parent entity. 07/04/2022 17:26:46
The annual report including audited profit and loss account, balance sheet, cash flow statement, directors report and auditor's report of the promoter for the immedietly preceding three financial years and where annual report is not available then the audited profit and loss account, balance sheet, cash flow statement and the auditor's report of the promoter for immedietly preceding three financial years and in case of newly incorporated or registered entity, such information shall be disclosed for the parent entity. 07/04/2022 17:28:47
ALLOTMENT DETAILS
Proforma of Agreement for Sale (As per Annexure A) 01/04/2022 13:29:13
Proforma of Allotment Letter 01/04/2022 13:29:27
ARCHITECT,ENGINEER & CA Certificates
Architect's Certificate in Form 2 27/10/2022 09:45:06
Architect's Certificate in Form 2 27/10/2022 09:45:37
Architect's Certificate in Form 2 07/01/2023 18:37:31
Architect's Certificate in Form 2 07/04/2023 15:59:25
Architect's Certificate in Form 2 06/07/2023 17:26:19
Architect's Certificate in Form 2 07/10/2023 16:27:22
Architect's Certificate in Form 2 06/01/2024 17:20:05
Architect's Certificate in Form 2 06/04/2024 17:26:04
Chartered Accountant's Certificate in Form 4 (in letter head) 06/12/2022 11:30:51
Chartered Accountant's Certificate in Form 4 (in letter head) 11/01/2023 15:53:13
Chartered Accountant's Certificate in Form 4 (in letter head) 13/01/2023 10:29:18
Chartered Accountant's Certificate in Form 4 (in letter head) 07/04/2023 19:41:21
Chartered Accountant's Certificate in Form 4 (in letter head) 06/07/2023 17:27:51
Chartered Accountant's Certificate in Form 4 (in letter head) 07/10/2023 18:14:47
Chartered Accountant's Certificate in Form 4 (in letter head) 10/10/2023 14:25:59
Chartered Accountant's Certificate in Form 4 (in letter head) 06/01/2024 17:18:43
Chartered Accountant's Certificate in Form 4 (in letter head) 06/04/2024 17:32:50
Declaration by the Promoter - Form No. 6
Engineer's Certificate in Form 3 06/12/2022 11:36:38
Engineer's Certificate in Form 3 06/12/2022 11:37:36
Engineer's Certificate in Form 3 07/01/2023 18:36:24
Engineer's Certificate in Form 3 07/04/2023 16:00:15
Engineer's Certificate in Form 3 06/07/2023 17:26:52
Engineer's Certificate in Form 3 07/10/2023 16:26:53
Engineer's Certificate in Form 3 06/01/2024 17:20:41
Engineer's Certificate in Form 3 06/04/2024 17:26:33
NOC and other Clearance
Clearance from Airport Authority of India 07/04/2022 17:40:03
Clearance from Coastal Zone Management Authority
Clearance from National Highways / Railways / Other Relevant Departments
Concurrence / Layout Approval of Town and Country planning department 07/04/2022 17:31:08
Consent to establish (Clearance from Pollution Control Board)
Consent to operate (Clearance from Pollution Control Board)
Environment Clearance
Final Fire NOC
If the project is proposed to be developed in Phases, an authenticated copy of license or land use permission, Building sanction plan or building permit for each of such phases (If applicable)
Initial NOC from Fire and Rescue department
Permission from Water and sewerage department
BROCHURE & OTHER DETAILS
Brochure / prospectus issued in regard to this project
Others
Sanction letters form bank for home loan tie-ups
Sanction letters from Bank for construction finance
PLAN OF DEVELOPMENT WORKS
Charts and the project schedule
List and details of common amenities
Other Plans to be executed in the proposed project
Plan for Drinking water service to be executed in the proposed project
Plan of firefighting to be executed in the proposed project
Plan of Use of renewable energy to be executed in the proposed project
The Plan of development works to be executed in the proposed project - Plan of fire fighting,evacuation services,use of renewable energy, drinking water service etc to be included-Charts and project schedule 01/04/2022 13:16:31
Land Owner Details
Upload Agreement / MoU Copy

Upload Photograph

Document Name Uploaded Document Uploaded Date
Brochure / prospectus issued in regard to this project 11/05/2023 13:18:08
Brochure / prospectus issued in regard to this project 11/05/2023 13:18:17
Brochure / prospectus issued in regard to this project 11/05/2023 13:18:32
Brochure / prospectus issued in regard to this project 11/05/2023 13:19:15
Brochure / prospectus issued in regard to this project 11/05/2023 13:19:26
Brochure / prospectus issued in regard to this project 11/05/2023 13:20:03
Brochure / prospectus issued in regard to this project 11/05/2023 13:20:20
Brochure / prospectus issued in regard to this project 11/05/2023 13:20:59
Brochure / prospectus issued in regard to this project 11/05/2023 13:20:59
Brochure / prospectus issued in regard to this project 11/05/2023 13:21:16
Brochure / prospectus issued in regard to this project 11/05/2023 13:21:29
Brochure / prospectus issued in regard to this project 11/05/2023 13:21:40
Photograph of each building 09/05/2023 16:30:41
Photograph of each building 09/05/2023 16:31:23
Photograph of each building 09/05/2023 16:32:20
Photograph of each building 09/05/2023 16:32:31
Photograph of each building 06/07/2023 17:54:44
Photograph of each building 07/10/2023 16:43:00
Photograph of each building 06/01/2024 18:09:37
Photograph of each building 06/04/2024 17:03:23

Litigations Related to the Project