General Information

K-RERA/PRJ/ERN/034/2024
OMG LAVENDER
OMG PROPERTIES PRIVATE LIMITED
Villas (Plots & Buildings)
28/10/2024
Click Here

Quarterly updated values

Project Information

OMG LAVENDER
Villas (Plots & Buildings)
30/11/2023
30/11/2028
Yes
No

Land Details

3763
14
1674
1674
0
14
0

Location Details of the Project Area

Re.survey 6/3/2 ,15/7/6
19120
KERALA
Ernakulam
Aluva
ANGAMALY
Elavoor kavala -puliyanam road
Near Peechanikad church
683572
Palayil poulose ,kunjappan,Eldho properties
property of poovathara alias and alukal yacob etc
Palayil poulose, madaparambil shabu properties
road and properties of palikodath saju and varghese

Mortgages

Promoter's Information - Other Than Individual


Company
OMG PROPERTIES PRIVATE LIMITED
Yes
No

Registered address of the Promoter

18/465-19,FIRST FLOOR
VICTORY CORNER
KOPPAM
KOPPAM VILLAGE OFFICE
KERALA
Palakkad
Palakkad
PALAKKAD MUNCIPALITY
678001

Address for official communication

18/465-19,FIRST FLOOR
VICTORY CORNER
KOPPAM
KOPPAM VILLAGE OFFICE
KERALA
Palakkad
Palakkad
PALAKKAD MUNCIPALITY
678001
Member Name Designation Address Contact Email Photo
SURESH V Authorized Signatory VANOPADATH,PULAPPATTASHERI, CHERUMUNDASSERY, , Ottappalam, KERALA, 679512 9072345255 sureshomgproperties@gmail.com View Photo
RAJANEESH V G NAIR Managing Director NELLIKKAPARAMBIL HOUSE, KK ROAD, , CHALAKKUDY, KERALA, 680307 9843620400 rajani.ve@gmail.com View Photo
GIREESH S Managing Director NO.A 102, VEDAM ENCLAVE, PATTANAM LTTERY ROAD, , Coimbatore South, TAMIL NADU, 641016 9843293237 gireesh7@gmail.com View Photo

Land owner details

Land owner Name Type of Land Owner PAN Number Type of Agreement/ Arrangement CreatedOn Office Number (With area code) Other Details
Land owner Name Type of Land Owner PAN Number Type of Agreement/ Arrangement CreatedOn Office Number (With area code) Other Details
Land owner Name Type of Land Owner PAN Number Type of Agreement/ Arrangement CreatedOn Office Number (With area code) Other Details
Land owner Name Type of Land Owner PAN Number Type of Agreement/ Arrangement CreatedOn Office Number (With area code) Other Details
Land owner Name Type of Land Owner PAN Number Type of Agreement/ Arrangement CreatedOn Office Number (With area code) Other Details
Land owner Name Type of Land Owner PAN Number Type of Agreement/ Arrangement CreatedOn Office Number (With area code) Other Details
Land owner Name Type of Land Owner PAN Number Type of Agreement/ Arrangement CreatedOn Office Number (With area code) Other Details

Promoter's Past Experience Details

Sr No. Project Name RERA registration number Project Address Land Area (In Sq mtrs) Details of payments pending Current status of the project Details of cases/ litigations related to the project Date of commencement Proposed date of completion Actual completion date Remarks (If any) Other relevant experience
1 NIL NIL 0 0 0 O 12/09/2018 18/03/2022 NA 0 0
//}

Promoter's Track Record

10
5
15
20000
9
10000

Building Permit Details

Building Permit Number Dated Type Date of Expiry Issued by Name of the Local body/ LSGI

Development Permit Details

Development Permit Number Dated Type Date of Expiry Issued by Name of the Local body/ LSGI

Building Details

Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 LD01 14/11/2028 1 1 2 0 1 0

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 100 4 4 0 0 4 112 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 LD02 14/11/2028 1 1 2 0 1 0

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 100 4 4 0 0 4 112 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 LD03 15/11/2028 1 1 2 0 1 0

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 100 4 4 0 0 4 112 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 LD04 14/11/2028 1 1 2 0 1 0

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 100 4 4 0 0 4 112 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
5 LD06 14/11/2028 1 1 2 0 1 0

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 100 4 4 0 0 4 112 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
6 LD05 14/11/2028 1 1 2 0 1 0

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 100 4 4 0 0 4 112 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
7 LD07 14/11/2028 1 1 2 0 1 0

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 100 4 4 0 0 4 112 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
8 LD08 14/11/2023 1 1 2 0 1 0

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 100 4 4 0 0 4 112 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
9 LD09 14/11/2028 1 1 2 0 1 0

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 115 4.66 5 0 0 5 126.66 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
10 LD10 14/11/2028 1 1 2 0 1 0

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 115 4.66 5 0 0 5 129.66 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
11 LD11 14/11/2028 1 1 2 0 1 0

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 115 4.66 5 0 0 5 129.66 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
12 LD12 14/11/2028 1 1 2 0 1 0

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 115 4.66 5 0 0 5 129.66 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
13 LD14 14/11/2028 1 1 2 0 1 0

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 115 4.66 5 0 0 5 129.66 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Building Name Proposed Date of Completion (As committed to allottees) Number of Basements Number of Podiums Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
14 LD15 14/11/2028 1 1 2 0 1 0

Apartments Type Details

Sr.No. Apartment Type Carpet Area Area of exclusive veranda Area of exclusive balcony Area of exclusive open terrace Share of common area Area of external wall Total area Proposed number of apartments Number of apartments Booked /Sold /Allotted
Current value Last Quarter value
1 Bangalow / Villas 115 4.66 5 0 0 5 129.66 1

Parking space for Sale Details

Sr.No. Parking Type No. of Garages/ Covered Parking Area (in Sqmts) No. of Garages/ Covered Parking booked
Current value Last Quarter value
1 Residential 0 0 0 NA

Task/Activity Details

Sr.No. Tasks / Activity Percentage of Work
Current value Last Quarter value
1 Excavation
2 Basement(s) and Plinth
3 Slabs of Super Structure
4 Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings
5 Sanitary Fittings
6 Electrical Fittings
7 Staircases, Lifts Wells
8 Overhead and Underground Water Tanks.
9 The external plumbing and external plastering
10 Completion of terraces floor each building
11

Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc

10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Plot Details

Area of Plot (In sqmts) Number of Plots Number of Plots Booked / Alloted / Sold
Current value Last Quarter value
3763 14 1 0

Common Areas and Facilities

Project Details

Name Proposed Number Progress of work done (In %)
Current value Last Quarter value
Number of Garages/ Covered Parking (In Numbers) (Common Area) :

Development Work

Common areas And Facilities, Amenities Proposed Percentage of completion Details
Current value Last Quarter value
Aggregate area of recreational open space :
Internal Roads & Footpaths :
Sewerage (Chamber, Lines, Septic tank, STP) :
Storm water drains :
Street lighting :
Sign Boards :
Water supply :

Professional Information

Professional Name RERA Certificate No. Professional Type Type of Contractor Registration Number Name of the firm Address of the firm Year of establishment Name of Promoters Associated with Key projects completed Type of Professional
Abdul hameed hafiz NA Architect NA CA/2022/148955 Arcus designs tirur 2015 omg properties omg vivante villas NA
yazeed ali p NA Engineer NA NA ARCUS tirur 2018 omg properties omg vivante villas NA
Radhakrishnan p NA Chartered Accountant NA ICAI217128 same same 2010 omg properties omg lifestyles NA

Uploaded Documents

Document Name Uploaded Document Remarks Uploaded Date
PROJECT DETAILS
Copy of Sanctioned Plans 27/12/2023 13:02:30
Copy of Sanctioned Plans 27/12/2023 13:02:44
Copy of Valid Building Permit 27/12/2023 13:01:58
Copy of Valid Building Permit 27/12/2023 13:02:13
Copy of Valid Development Permit 01/12/2023 13:16:16
Detailed technical specifications to be adopted in the project 27/12/2023 16:21:21
Details of Association Formed
Development certificate(for plots and villas)
Layout approval plan 01/12/2023 13:17:44
Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points 02/12/2023 13:34:04
Occupancy Certificate
Site Plan / Site Map
LAND DETAILS
Copy of latest Land Tax Receipt 01/12/2023 13:24:29
Copy of latest Land Tax Receipt land tax for total cents 30/01/2024 12:52:51
Copy of latest Land Tax Receipt land tax for total cents 30/01/2024 13:02:09
Copy of Title Deed 01/12/2023 13:22:50
Copy of Title Deed Base main document 30/01/2024 12:49:38
Copy of Title Deed another part owner transfer document 30/01/2024 12:51:49
Copy of Title Deed another part owner transfer document 30/01/2024 12:51:49
Details of Encumbrance 01/12/2023 13:21:43
Land title search report (From an advocate as specified in Rule 17) 01/12/2023 13:25:42
Proforma of Conveyance Deed / Sales Deed 09/12/2023 12:06:09
PROMOTER DETAILS
Declaration in Form B 02/12/2023 13:20:00
The annual report including audited profit and loss account, balance sheet, cash flow statement, directors report and auditor's report of the promoter for the immediately preceding three financial years and where annual report is not available then the audited profit and loss account, balance sheet, cash flow statement and the auditor's report of the promoter for immediately preceding three financial years and in case of newly incorporated or registered entity, such information shall be disclosed for the parent entity. 01/12/2023 13:28:57
The annual report including audited profit and loss account, balance sheet, cash flow statement, directors report and auditor's report of the promoter for the immediately preceding three financial years and where annual report is not available then the audited profit and loss account, balance sheet, cash flow statement and the auditor's report of the promoter for immediately preceding three financial years and in case of newly incorporated or registered entity, such information shall be disclosed for the parent entity. 01/12/2023 13:29:26
The annual report including audited profit and loss account, balance sheet, cash flow statement, directors report and auditor's report of the promoter for the immediately preceding three financial years and where annual report is not available then the audited profit and loss account, balance sheet, cash flow statement and the auditor's report of the promoter for immediately preceding three financial years and in case of newly incorporated or registered entity, such information shall be disclosed for the parent entity. 02/12/2023 13:17:00
The annual report including audited profit and loss account, balance sheet, cash flow statement, directors report and auditor's report of the promoter for the immediately preceding three financial years and where annual report is not available then the audited profit and loss account, balance sheet, cash flow statement and the auditor's report of the promoter for immediately preceding three financial years and in case of newly incorporated or registered entity, such information shall be disclosed for the parent entity. 02/12/2023 13:17:26
ALLOTMENT DETAILS
Proforma of Agreement for Sale (As per Annexure A) 08/12/2023 12:09:00
Proforma of Agreement for Sale (As per Annexure A) Changes made as per scrutiny points 03/02/2024 12:55:09
Proforma of Agreement for Sale (As per Annexure A) changes done as per scruitny 03/02/2024 13:06:25
Proforma of Allotment Letter 01/12/2023 13:42:37
ARCHITECT,ENGINEER & CA Certificates
Architect's Certificate in Form 2 06/07/2024 12:26:26
Architect's Certificate in Form 2 05/10/2024 17:19:29
Chartered Accountant's Certificate in Form 4 (in letter head) 25/05/2024 16:01:13
Chartered Accountant's Certificate in Form 4 (in letter head) 05/07/2024 14:24:48
Chartered Accountant's Certificate in Form 4 (in letter head) 05/10/2024 16:31:43
Declaration by the Promoter - Form No. 6
Engineer's Certificate in Form 3
NOC and other Clearance
Clearance from Airport Authority of India not applicable 08/12/2023 12:13:34
Clearance from Coastal Zone Management Authority not applicable 08/12/2023 12:12:38
Clearance from National Highways / Railways / Other Relevant Departments not applicable 08/12/2023 12:13:52
Concurrence / Layout Approval of Town and Country planning department NOT applicable as lesser plots, 08/12/2023 12:11:56
Consent to establish (Clearance from Pollution Control Board) Not applicable as lesser plot villas 01/02/2024 13:18:43
Consent to operate (Clearance from Pollution Control Board) Not applicable as lesser plot villas 01/02/2024 13:19:14
Environment Clearance not applicable 08/12/2023 12:12:17
Final Fire NOC
If the project is proposed to be developed in Phases, an authenticated copy of license or land use permission, Building sanction plan or building permit for each of such phases (If applicable) ONE phase only, 01/02/2024 13:19:46
Initial NOC from Fire and Rescue department not applicable 08/12/2023 12:14:02
Permission from Water and sewerage department not applicable 08/12/2023 12:12:28
BROCHURE & OTHER DETAILS
Brochure / prospectus issued in regard to this project
Others fee calculation sheet , 27/12/2023 16:51:48
Others REQUEST LETTER TO HOLD THE APPLICATION 17/01/2024 14:15:37
Sanction letters form bank for home loan tie-ups
Sanction letters from Bank for construction finance
PLAN OF DEVELOPMENT WORKS
Charts and the project schedule 08/12/2023 14:16:21
List and details of common amenities 08/12/2023 14:16:07
Other Plans to be executed in the proposed project
Others
Plan for Drinking water service to be executed in the proposed project
Plan of firefighting to be executed in the proposed project
Plan of Use of renewable energy to be executed in the proposed project
Land Owner Details
Upload Agreement / MoU Copy 02/12/2023 12:36:38
Upload Agreement / MoU Copy 02/12/2023 12:37:59
Upload Agreement / MoU Copy 02/12/2023 12:38:34
Upload Agreement / MoU Copy 02/12/2023 12:39:36
Upload Agreement / MoU Copy 02/12/2023 12:40:26
Upload Agreement / MoU Copy 02/12/2023 12:41:05
Upload Agreement / MoU Copy 02/12/2023 12:41:33

Upload Photograph

Document Name Uploaded Document Uploaded Date
Photograph of each building 05/10/2024 11:34:32
Photographs of common areas and internal infrastructure 09/07/2024 16:10:10

Litigations Related to the Project